TJ21预制箱梁首件总结报告 下载本文

内容发布更新时间 : 2024/5/14 19:34:03星期一 下面是文章的全部内容请认真阅读。

目 录

1.工程概况 .............................................................................................................................................................2 2.首件预制箱梁目的 ...........................................................................................................................................2 3.施工准备 .............................................................................................................................................................3

3.1现场准备 ................................................................................................................................................3 3.2技术准备 ................................................................................................................................................3 3.3材料准备 ................................................................................................................................................3

3.3.1.钢筋、钢绞线 ...........................................................................................................................3 3.3.2.水泥 .............................................................................................................................................3 3.3.3.砂、石料等材料 ......................................................................................................................4 3.3.4.外加剂.........................................................................................................................................4 3.4人员、机械、设备 ..............................................................................................................................4 四、施工方案 .......................................................................................................................................................6

4.1、施工工艺流程 ....................................................................................................................................6 4.2、施工方案的确定 ...............................................................................................................................7

4.2.1台座 .............................................................................................................................................7 4.2.2钢筋及预应力管道的制作安装 ..........................................................................................8 4.2.3钢绞线的下料........................................................................................................................ 10 4.2.4安装波纹管道........................................................................................................................ 11 4.3、模板制作与安装 ............................................................................................................................ 12 4.4、堵头模板的安装 ............................................................................................................................ 13 4.5、箱梁砼的浇筑 ................................................................................................................................. 14 4.6、拆模养护 .......................................................................................................................................... 15 4.7、穿束 ................................................................................................................................................... 16 4.8、预应力拉 .......................................................................................................................................... 16 4.9、孔道压浆 .......................................................................................................................................... 18 4.10、堵头与封锚 ................................................................................................................................... 19 4.11、移梁(存放、固定) ................................................................................................................ 20 五、首件工程中存在的不足 ......................................................................................................................... 20 六、施工注意事项和需要改进的地方 ...................................................................................................... 21 七、综合评价及总结 ....................................................................................................................................... 22

预制箱梁首件工程施工技术总结

为了确保我合同段的预制箱梁工程质量符合设计要求及技术标准,我标段选定竹子坑1#大桥30m 预制箱梁作为首件工程。依照交通厅《粤交基【2015】130号》文件:“每个预制场前3片梁的锚下预应力必检”的要求,我标段预制箱梁选取了竹子坑1#大桥右1-2中梁、右1-3中梁、右2-2中梁作为首件工程施工、目前3片箱梁施工已全部完成。

1.工程概况

梁场负责预制 K177+374 巷尾村中桥、K179+787.7 竹子坑1#大桥、K180+054 竹子坑2#中桥、 K181+192.7 竹子坑3#大桥、K181+908.5大船顶1#中桥、K182+832.8大船顶2#大桥以及 LK0+730.7 匝道桥的箱梁预制,预制梁共计259片,其中20米箱梁48片,25米箱梁179片,30米箱梁32片。

梁场预制任务

序号 1 2 3 4 5 6 7 中心桩号桥梁名称 K177+374 巷尾村中桥 K179+787.7 竹子坑1#大桥 K180+054 竹子坑2#中桥 K181+192.7 竹子坑3#大桥 K181+908.5 大船顶1#中桥 K182+832.8 大船顶2#大桥 LKO+730.7 L匝道桥 上部构造工程量 25m小箱梁29片 30m小箱梁32片 20m小箱梁24片 25m小箱梁32片 20m小箱梁24片 25m小箱梁88片 25m小箱梁30片 斜交角 120度 120 90度 105度 105度 105度 75度 75度 2.首件预制箱梁目的

通过首件的施工,取得相关的技术参数,确定拟定施工方案的可行性,为后续施工总结

相关经验;通过首件工程施工,结合预制箱梁施工的特点,来确定最优的施工工艺和施工组织。根据首件工程的各项质量指标进行综合总结评价,对施工质量存在的不足之处分析原因、提出改进措施。指导后续施工,预防后续施工可能产生的各种质量问题。

3.施工准备

3.1现场准备

(1)场便道硬化完成,满足通行及施工要求。

(2)施工用水:从附近水井引水至施工现场以保证施工过程用水。

(3)施工用电:施工用电主要通过专门的线路进行电力供应满足施工作业。 另自备250KW 发电机一台作备用电源 。

(4)梁厂验收已完成。

(5)模板已进场验收合格,经过试拼满足设计及规要求。

3.2技术准备

已完成对现有施工图纸的审核,并组织专人培训学习施组相关资料;首件施工方案、技术及安全交底已经下发到作业人员手里。测量放样数据经复核无误,原材经试验满足要求,施工机具已进行标定,混凝土配合比报告已经审批完成。

3.3材料准备 3.3.1.钢筋、钢绞线

(1)进场时,每批钢筋、钢绞线须由同一品牌、规格、生产工艺和交货状态的 材料组成。均须办理进场手续,并提供产品合格证。钢筋、钢绞线按不同钢种、等级、 牌号、规格及生产厂家分类堆放,不得混杂,应挂牌标示。根据标准化管理,钢筋场制作了钢筋堆放台。

(2)钢筋应进行物理力学性能、冷弯性能、延伸率和可焊性等试验;钢绞线应 进行弹性模量、松弛率等试验;经试验不合格的钢筋和钢绞线,严禁使用。

3.3.2.水泥

(1)每批灌装水泥须由同一厂家、品牌、规格和生产批次的水泥组成。每批水 泥进场,必须提供产品合格证。

(2)进场时灌装水泥进行强度、凝结时间和安定性等试验,经试验不合格的水泥,严